The Mercy Hub Update - MAY 20th 2018


LATEST UPDATE MAY 20:
This week the redevelopment of the basement area into the Mercy Hub, has included the creation of structural openings to the new entrance, meeting room, kitchen and toilet areas. Construction work to the walls at the base of the stairs and courtyard access area has commenced and some boarding and plastering work has taken place in the smaller meeting room. Progress is ongoing with electrics, fire provision and access control systems.

Building work continues in the Cathedral basement for the new Mercy Hub